Utb-United Technology, Inc: New York City Government Payments

as recorded by New York City: UTB-UNITED TECHNOLOGY, INC

Utb-United Technology, Inc is the 378th-largest recipient of New York City government payments tracked by SpendLedger, and ranks 60th in CONSTRUCTION-BUILDINGS spending. Its payments amount to 0.3% of everything the School Construction Authority has paid vendors in that span. Payments to it fell 49% year over year.

Primary spending category: CONSTRUCTION-BUILDINGS

$187,176,160total received
2,231payments
7agencies
Jan 5, 2010Jun 11, 2025first / last payment
Follow this vendorGet an email when New York City publishes new payments to Utb-United Technology, Inc. No spam.

Payments by fiscal year

FY 2025$7,487,347
FY 2024$14,690,157
FY 2023$20,886,038
FY 2022$16,672,185
FY 2021$9,241,973
FY 2020$20,839,924
FY 2019$18,070,128
FY 2018$15,220,897
FY 2017$4,565,629
FY 2016$10,882,336
FY 2015$13,962,011
FY 2014$11,681,538
FY 2013$7,252,123
FY 2012$7,284,911
FY 2011$5,322,346
FY 2010$3,116,618

Payments by fiscal year and agency

Fiscal yearAgencyPaymentsTotal
FY 2025School Construction Authority117$7,388,594
FY 2025Department of Parks and Recreation16$98,752
FY 2024School Construction Authority161$14,690,157
FY 2023School Construction Authority207$20,774,259
FY 2023Department of Parks and Recreation30$111,779
FY 2022School Construction Authority219$16,672,185
FY 2021School Construction Authority119$7,998,909
FY 2021Department of Transportation43$943,375
FY 2021Department of Parks and Recreation44$294,170
FY 2021Department of Environmental Protection3$6,569
FY 2021Department of Design and Construction3-$1,050
FY 2020School Construction Authority232$20,447,675
FY 2020Department of Parks and Recreation12$365,168
FY 2020Department of Environmental Protection10$27,082
FY 2019School Construction Authority96$14,520,432
FY 2019Department of Parks and Recreation41$3,361,200
FY 2019Department of Environmental Protection3$188,495
FY 2018Department of Parks and Recreation90$11,613,050
FY 2018School Construction Authority40$3,240,628
FY 2018Department of Transportation5$228,490
FY 2018Department of Environmental Protection2$138,702
FY 2018Department of Homeless Services4$27
FY 2017Department of Parks and Recreation27$2,377,823
FY 2017Department of Transportation9$1,260,024
FY 2017School Construction Authority12$624,167
FY 2017Department of Environmental Protection3$171,795
FY 2017Department of Cultural Affairs1$113,819
FY 2017Department of Homeless Services7$18,000
FY 2016School Construction Authority18$6,407,072
FY 2016Department of Transportation15$2,974,489
FY 2016Department of Cultural Affairs49$668,038
FY 2016Department of Environmental Protection25$481,788
FY 2016Department of Parks and Recreation6$350,842
FY 2016Department of Design and Construction1$107
FY 2015School Construction Authority26$8,125,106
FY 2015Department of Cultural Affairs21$2,918,639
FY 2015Department of Transportation10$1,942,475
FY 2015Department of Environmental Protection25$833,155
FY 2015Department of Parks and Recreation4$115,535
FY 2015Department of Homeless Services12$27,100
FY 2014School Construction Authority19$3,187,283
FY 2014Department of Environmental Protection34$3,076,225
FY 2014Department of Cultural Affairs19$2,836,624
FY 2014Department of Parks and Recreation4$1,547,654
FY 2014Department of Transportation3$1,033,752
FY 2013Department of Environmental Protection31$6,424,448
FY 2013School Construction Authority32$827,675
FY 2012Department of Environmental Protection29$3,795,667
FY 2012School Construction Authority74$3,456,794
FY 2012Department of Homeless Services64$32,450
FY 2011School Construction Authority69$3,563,682
FY 2011Department of Environmental Protection16$1,758,014
FY 2011Department of Homeless Services1$650
FY 2010School Construction Authority57$2,101,651
FY 2010Department of Environmental Protection11$1,014,966
Total2,231$187,176,160

What the payments were for

Spending categories exactly as New York City government codes them in its own accounting; we do not reclassify.

CategoryPaymentsTotalFirst / last
MAINT & REP GENERAL84$78,200May 16, 2011 Jun 14, 2017
IOTB CONSTRUCTION425$35,907,136Jan 11, 2010 Oct 24, 2024
CONTRACTUAL SERVICES GENERAL13$2,870,907Jul 31, 2017 Nov 1, 2018
PROMPT PAYMENT INTEREST20$256Feb 25, 2016 Sep 7, 2022
N/A4$225,995Jun 6, 2018 Feb 21, 2019
CONSTRUCTION-BUILDINGS1,649$146,894,692Jan 5, 2010 Jun 11, 2025
POLLUTION REMEDIATION OBLIGATIONS30$1,201,075Jan 6, 2011 Oct 21, 2013
<Non-Applicable Expenditure Object>6-$2,100Dec 21, 2012 Aug 26, 2020

Largest payments by fiscal year

The biggest individual payments in each fiscal year, up to 20 per year. Where the source publishes a purchase order behind a payment, the PO description appears; older payments may carry a bare PO reference because the government's published PO files do not reach back that far.

Download this table as CSV (free, with source citation on every row)

FY 2025top 20 of 133 payments$7,487,347
DateAgencyAmountCategoryPurchase order
Dec 19, 2024School Construction Authority$653,343.50CONSTRUCTION-BUILDINGS
Dec 11, 2024School Construction Authority$643,197.50CONSTRUCTION-BUILDINGS
Nov 20, 2024School Construction Authority$643,197.50CONSTRUCTION-BUILDINGS
Sep 27, 2024School Construction Authority$389,580.75CONSTRUCTION-BUILDINGS
Nov 18, 2024School Construction Authority$334,107.26CONSTRUCTION-BUILDINGS
Oct 28, 2024School Construction Authority$274,926.50CONSTRUCTION-BUILDINGS
Oct 28, 2024School Construction Authority$262,611.96CONSTRUCTION-BUILDINGS
Sep 3, 2024School Construction Authority$230,915.17CONSTRUCTION-BUILDINGS
Aug 2, 2024School Construction Authority$216,194.88CONSTRUCTION-BUILDINGS
Oct 28, 2024School Construction Authority$205,641.27CONSTRUCTION-BUILDINGS
Jun 11, 2025School Construction Authority$181,602.00CONSTRUCTION-BUILDINGS
Feb 25, 2025School Construction Authority$175,649.66CONSTRUCTION-BUILDINGS
Sep 27, 2024School Construction Authority$164,806.00CONSTRUCTION-BUILDINGS
Apr 21, 2025School Construction Authority$164,302.50CONSTRUCTION-BUILDINGS
Feb 7, 2025School Construction Authority$157,253.72CONSTRUCTION-BUILDINGS
Mar 27, 2025School Construction Authority$155,964.83CONSTRUCTION-BUILDINGS
Feb 13, 2025School Construction Authority$144,854.98CONSTRUCTION-BUILDINGS
Jun 11, 2025School Construction Authority$143,701.51CONSTRUCTION-BUILDINGS
Jun 4, 2025School Construction Authority$143,701.51CONSTRUCTION-BUILDINGS
May 19, 2025School Construction Authority$141,075.00CONSTRUCTION-BUILDINGS
FY 2024top 20 of 161 payments$14,690,157
DateAgencyAmountCategoryPurchase order
Aug 14, 2023School Construction Authority$786,899.25CONSTRUCTION-BUILDINGS
Aug 14, 2023School Construction Authority$778,525.00CONSTRUCTION-BUILDINGS
Feb 15, 2024School Construction Authority$602,311.40CONSTRUCTION-BUILDINGS
Aug 10, 2023School Construction Authority$585,722.69CONSTRUCTION-BUILDINGS
Jul 18, 2023School Construction Authority$501,936.30CONSTRUCTION-BUILDINGS
Jul 14, 2023School Construction Authority$486,495.00CONSTRUCTION-BUILDINGS
Jul 14, 2023School Construction Authority$464,258.35CONSTRUCTION-BUILDINGS
Aug 18, 2023School Construction Authority$456,738.15CONSTRUCTION-BUILDINGS
Nov 22, 2023School Construction Authority$446,737.50CONSTRUCTION-BUILDINGS
Aug 18, 2023School Construction Authority$432,975.79CONSTRUCTION-BUILDINGS
Oct 2, 2023School Construction Authority$420,232.50CONSTRUCTION-BUILDINGS
Oct 2, 2023School Construction Authority$417,097.50CONSTRUCTION-BUILDINGS
Oct 18, 2023School Construction Authority$356,250.00CONSTRUCTION-BUILDINGS
Aug 14, 2023School Construction Authority$348,032.50CONSTRUCTION-BUILDINGS
Oct 2, 2023School Construction Authority$344,904.15CONSTRUCTION-BUILDINGS
May 22, 2024School Construction Authority$306,860.63CONSTRUCTION-BUILDINGS
Mar 28, 2024School Construction Authority$306,860.63CONSTRUCTION-BUILDINGS
Mar 12, 2024School Construction Authority$247,047.50CONSTRUCTION-BUILDINGS
Jul 18, 2023School Construction Authority$243,799.45CONSTRUCTION-BUILDINGS
Nov 22, 2023School Construction Authority$237,424.00CONSTRUCTION-BUILDINGS
FY 2023top 20 of 237 payments$20,886,038
DateAgencyAmountCategoryPurchase order
Jun 5, 2023School Construction Authority$1,023,653.14CONSTRUCTION-BUILDINGS
Sep 20, 2022School Construction Authority$683,183.32CONSTRUCTION-BUILDINGS
Jun 13, 2023School Construction Authority$669,253.15CONSTRUCTION-BUILDINGS
Apr 12, 2023School Construction Authority$660,865.90CONSTRUCTION-BUILDINGS
Dec 7, 2022School Construction Authority$630,248.02CONSTRUCTION-BUILDINGS
May 4, 2023School Construction Authority$609,087.42CONSTRUCTION-BUILDINGS
Jun 13, 2023School Construction Authority$588,240.00CONSTRUCTION-BUILDINGS
May 4, 2023School Construction Authority$573,196.25CONSTRUCTION-BUILDINGS
Mar 6, 2023School Construction Authority$565,250.00CONSTRUCTION-BUILDINGS
Jun 28, 2023School Construction Authority$536,085.00CONSTRUCTION-BUILDINGS
May 4, 2023School Construction Authority$531,002.50CONSTRUCTION-BUILDINGS
Jun 28, 2023School Construction Authority$468,540.00CONSTRUCTION-BUILDINGS
Oct 7, 2022School Construction Authority$427,980.24CONSTRUCTION-BUILDINGS
Sep 20, 2022School Construction Authority$414,465.36CONSTRUCTION-BUILDINGS
Mar 6, 2023School Construction Authority$408,936.81CONSTRUCTION-BUILDINGS
Jun 5, 2023School Construction Authority$382,470.00CONSTRUCTION-BUILDINGS
Jul 21, 2022School Construction Authority$351,936.16CONSTRUCTION-BUILDINGS
May 22, 2023School Construction Authority$343,177.96CONSTRUCTION-BUILDINGS
Apr 24, 2023School Construction Authority$326,435.42CONSTRUCTION-BUILDINGS
Jul 6, 2022School Construction Authority$306,834.72CONSTRUCTION-BUILDINGS
FY 2022top 20 of 219 payments$16,672,185
DateAgencyAmountCategoryPurchase order
Oct 19, 2021School Construction Authority$1,479,917.46CONSTRUCTION-BUILDINGS
Aug 18, 2021School Construction Authority$815,278.75CONSTRUCTION-BUILDINGS
Mar 2, 2022School Construction Authority$396,548.05CONSTRUCTION-BUILDINGS
Mar 8, 2022School Construction Authority$396,548.05CONSTRUCTION-BUILDINGS
May 16, 2022School Construction Authority$257,315.46CONSTRUCTION-BUILDINGS
Jul 19, 2021School Construction Authority$256,824.77CONSTRUCTION-BUILDINGS
Aug 16, 2021School Construction Authority$246,678.23CONSTRUCTION-BUILDINGS
Jan 12, 2022School Construction Authority$242,714.31CONSTRUCTION-BUILDINGS
Dec 9, 2021School Construction Authority$230,517.57CONSTRUCTION-BUILDINGS
Aug 24, 2021School Construction Authority$230,359.38CONSTRUCTION-BUILDINGS
Oct 22, 2021School Construction Authority$229,612.00CONSTRUCTION-BUILDINGS
Jun 17, 2022School Construction Authority$229,069.03CONSTRUCTION-BUILDINGS
Nov 18, 2021School Construction Authority$228,878.75CONSTRUCTION-BUILDINGS
Jun 13, 2022School Construction Authority$228,000.00CONSTRUCTION-BUILDINGS
Nov 12, 2021School Construction Authority$222,461.83CONSTRUCTION-BUILDINGS
Aug 24, 2021School Construction Authority$216,828.00CONSTRUCTION-BUILDINGS
Jan 6, 2022School Construction Authority$216,687.40CONSTRUCTION-BUILDINGS
Sep 21, 2021School Construction Authority$191,377.50CONSTRUCTION-BUILDINGS
Jun 13, 2022School Construction Authority$187,298.52CONSTRUCTION-BUILDINGS
Jan 24, 2022School Construction Authority$185,971.81CONSTRUCTION-BUILDINGS
FY 2021top 20 of 212 payments$9,241,973
DateAgencyAmountCategoryPurchase order
May 6, 2021School Construction Authority$986,394.50CONSTRUCTION-BUILDINGS
Aug 26, 2020Department of Transportation$529,994.00CONSTRUCTION-BUILDINGS
Apr 13, 2021School Construction Authority$466,269.50CONSTRUCTION-BUILDINGS
Jan 6, 2021School Construction Authority$336,585.00CONSTRUCTION-BUILDINGS
Apr 19, 2021School Construction Authority$304,102.66CONSTRUCTION-BUILDINGS
Jun 28, 2021School Construction Authority$302,560.75CONSTRUCTION-BUILDINGS
Feb 24, 2021School Construction Authority$300,437.50CONSTRUCTION-BUILDINGS
Dec 14, 2020School Construction Authority$240,995.10CONSTRUCTION-BUILDINGS
Dec 14, 2020School Construction Authority$239,991.02CONSTRUCTION-BUILDINGS
Feb 9, 2021School Construction Authority$213,287.27CONSTRUCTION-BUILDINGS
Jan 6, 2021School Construction Authority$191,520.00CONSTRUCTION-BUILDINGS
Jun 7, 2021School Construction Authority$190,123.50CONSTRUCTION-BUILDINGS
Jan 6, 2021School Construction Authority$164,957.09CONSTRUCTION-BUILDINGS
Jan 13, 2021School Construction Authority$164,140.05CONSTRUCTION-BUILDINGS
Mar 30, 2021School Construction Authority$147,363.05CONSTRUCTION-BUILDINGS
May 25, 2021School Construction Authority$144,297.93CONSTRUCTION-BUILDINGS
Mar 30, 2021School Construction Authority$142,500.00CONSTRUCTION-BUILDINGS
Feb 4, 2021School Construction Authority$127,713.92CONSTRUCTION-BUILDINGS
May 6, 2021School Construction Authority$125,093.29CONSTRUCTION-BUILDINGS
Jun 28, 2021School Construction Authority$118,750.00CONSTRUCTION-BUILDINGS
FY 2020top 20 of 254 payments$20,839,924
DateAgencyAmountCategoryPurchase order
Sep 30, 2019School Construction Authority$569,335.00CONSTRUCTION-BUILDINGS
Nov 13, 2019School Construction Authority$482,327.35CONSTRUCTION-BUILDINGS
Oct 17, 2019School Construction Authority$479,245.73CONSTRUCTION-BUILDINGS
Jul 22, 2019School Construction Authority$477,351.25CONSTRUCTION-BUILDINGS
Aug 15, 2019School Construction Authority$469,964.86CONSTRUCTION-BUILDINGS
Oct 16, 2019School Construction Authority$454,708.00CONSTRUCTION-BUILDINGS
Dec 18, 2019School Construction Authority$444,248.03CONSTRUCTION-BUILDINGS
Jul 24, 2019School Construction Authority$436,592.26CONSTRUCTION-BUILDINGS
Jul 2, 2019School Construction Authority$435,373.98CONSTRUCTION-BUILDINGS
Nov 6, 2019School Construction Authority$420,215.40CONSTRUCTION-BUILDINGS
Jul 2, 2019School Construction Authority$406,600.00CONSTRUCTION-BUILDINGS
Sep 18, 2019School Construction Authority$404,838.05CONSTRUCTION-BUILDINGS
Sep 12, 2019School Construction Authority$390,342.27CONSTRUCTION-BUILDINGS
Aug 19, 2019School Construction Authority$323,253.70CONSTRUCTION-BUILDINGS
Dec 16, 2019School Construction Authority$322,097.50CONSTRUCTION-BUILDINGS
Aug 13, 2019School Construction Authority$318,005.39CONSTRUCTION-BUILDINGS
Feb 3, 2020School Construction Authority$300,186.81CONSTRUCTION-BUILDINGS
Oct 24, 2019School Construction Authority$287,175.97CONSTRUCTION-BUILDINGS
Nov 27, 2019School Construction Authority$283,745.81CONSTRUCTION-BUILDINGS
Jan 30, 2020School Construction Authority$280,273.75CONSTRUCTION-BUILDINGS
FY 2019top 20 of 140 payments$18,070,128
DateAgencyAmountCategoryPurchase order
Sep 21, 2018School Construction Authority$704,850.50CONSTRUCTION-BUILDINGS
Apr 25, 2019School Construction Authority$658,064.52CONSTRUCTION-BUILDINGS
May 21, 2019School Construction Authority$607,216.25CONSTRUCTION-BUILDINGS
Oct 11, 2018School Construction Authority$570,712.50CONSTRUCTION-BUILDINGS
Jul 18, 2018School Construction Authority$555,455.41CONSTRUCTION-BUILDINGS
Aug 21, 2018School Construction Authority$546,679.78CONSTRUCTION-BUILDINGS
May 14, 2019School Construction Authority$466,837.75CONSTRUCTION-BUILDINGS
Oct 23, 2018School Construction Authority$460,027.20CONSTRUCTION-BUILDINGS
Jul 11, 2018School Construction Authority$430,480.15CONSTRUCTION-BUILDINGS
Sep 12, 2018School Construction Authority$429,186.25CONSTRUCTION-BUILDINGS
Apr 9, 2019School Construction Authority$428,488.00CONSTRUCTION-BUILDINGS
Jan 10, 2019School Construction Authority$399,545.77CONSTRUCTION-BUILDINGS
Jun 13, 2019School Construction Authority$365,023.25CONSTRUCTION-BUILDINGS
Jan 4, 2019School Construction Authority$361,425.16CONSTRUCTION-BUILDINGS
Nov 23, 2018School Construction Authority$358,078.75CONSTRUCTION-BUILDINGS
Apr 12, 2019School Construction Authority$340,290.00CONSTRUCTION-BUILDINGS
Jan 17, 2019School Construction Authority$334,637.50CONSTRUCTION-BUILDINGS
Jan 18, 2019Department of Parks and Recreation$274,003.75IOTB CONSTRUCTION
Jul 31, 2018School Construction Authority$267,336.65CONSTRUCTION-BUILDINGS
Dec 24, 2018Department of Parks and Recreation$263,984.10IOTB CONSTRUCTION
FY 2018top 20 of 141 payments$15,220,897
DateAgencyAmountCategoryPurchase order
Oct 16, 2017Department of Parks and Recreation$1,104,214.45CONTRACTUAL SERVICES GENERAL
Nov 22, 2017Department of Parks and Recreation$712,348.00CONTRACTUAL SERVICES GENERAL
Nov 29, 2017School Construction Authority$638,132.10CONSTRUCTION-BUILDINGS
Jul 31, 2017Department of Parks and Recreation$628,696.70CONTRACTUAL SERVICES GENERAL
Aug 25, 2017Department of Parks and Recreation$510,681.05IOTB CONSTRUCTION
Aug 10, 2017Department of Parks and Recreation$506,350.00IOTB CONSTRUCTION
Aug 25, 2017Department of Parks and Recreation$468,111.08IOTB CONSTRUCTION
Jun 21, 2018School Construction Authority$464,618.59CONSTRUCTION-BUILDINGS
Aug 10, 2017Department of Parks and Recreation$456,407.55IOTB CONSTRUCTION
Dec 26, 2017Department of Parks and Recreation$407,419.94IOTB CONSTRUCTION
Aug 25, 2017Department of Parks and Recreation$375,936.85IOTB CONSTRUCTION
Aug 25, 2017Department of Parks and Recreation$346,230.35IOTB CONSTRUCTION
Dec 29, 2017School Construction Authority$319,088.85CONSTRUCTION-BUILDINGS
Nov 13, 2017Department of Parks and Recreation$296,493.57IOTB CONSTRUCTION
Nov 13, 2017Department of Parks and Recreation$286,421.68IOTB CONSTRUCTION
Aug 25, 2017Department of Parks and Recreation$280,851.35IOTB CONSTRUCTION
Sep 13, 2017Department of Parks and Recreation$267,131.45CONTRACTUAL SERVICES GENERAL
Dec 26, 2017Department of Parks and Recreation$259,115.56IOTB CONSTRUCTION
May 16, 2018School Construction Authority$236,279.86CONSTRUCTION-BUILDINGS
Jun 18, 2018Department of Parks and Recreation$203,946.00IOTB CONSTRUCTION
FY 2017top 20 of 59 payments$4,565,629
DateAgencyAmountCategoryPurchase order
Jun 16, 2017Department of Parks and Recreation$354,793.29IOTB CONSTRUCTION
Jul 29, 2016Department of Transportation$316,307.00CONSTRUCTION-BUILDINGS
Jun 16, 2017Department of Parks and Recreation$279,599.78IOTB CONSTRUCTION
Apr 20, 2017Department of Parks and Recreation$241,563.16IOTB CONSTRUCTION
Sep 16, 2016Department of Transportation$239,545.64CONSTRUCTION-BUILDINGS
Dec 1, 2016Department of Transportation$229,705.36IOTB CONSTRUCTION
Apr 20, 2017Department of Parks and Recreation$220,479.80IOTB CONSTRUCTION
Apr 20, 2017Department of Parks and Recreation$220,479.80IOTB CONSTRUCTION
Oct 27, 2016School Construction Authority$191,501.60CONSTRUCTION-BUILDINGS
Jun 9, 2017Department of Parks and Recreation$191,337.60IOTB CONSTRUCTION
Aug 1, 2016Department of Transportation$171,256.92IOTB CONSTRUCTION
Jun 9, 2017Department of Parks and Recreation$171,123.50IOTB CONSTRUCTION
Apr 3, 2017Department of Transportation$148,301.12IOTB CONSTRUCTION
Apr 20, 2017Department of Parks and Recreation$133,076.00IOTB CONSTRUCTION
Jun 9, 2017Department of Parks and Recreation$123,994.46IOTB CONSTRUCTION
Apr 20, 2017Department of Parks and Recreation$123,956.00IOTB CONSTRUCTION
Jun 23, 2017School Construction Authority$119,928.00CONSTRUCTION-BUILDINGS
Jan 3, 2017Department of Cultural Affairs$113,819.31CONSTRUCTION-BUILDINGS
Dec 19, 2016Department of Transportation$88,047.50CONSTRUCTION-BUILDINGS
Jun 9, 2017Department of Parks and Recreation$87,145.40IOTB CONSTRUCTION
FY 2016top 20 of 114 payments$10,882,336
DateAgencyAmountCategoryPurchase order
Jun 1, 2016School Construction Authority$1,560,020.15CONSTRUCTION-BUILDINGS
Aug 12, 2015School Construction Authority$922,682.75CONSTRUCTION-BUILDINGS
Sep 21, 2015School Construction Authority$794,217.48CONSTRUCTION-BUILDINGS
Oct 23, 2015School Construction Authority$660,962.50CONSTRUCTION-BUILDINGS
Jul 8, 2015School Construction Authority$559,382.99CONSTRUCTION-BUILDINGS
Dec 23, 2015Department of Transportation$473,912.05IOTB CONSTRUCTION
Jun 22, 2016Department of Transportation$461,686.00CONSTRUCTION-BUILDINGS
Sep 28, 2015Department of Transportation$459,445.50CONSTRUCTION-BUILDINGS
Nov 6, 2015Department of Transportation$307,622.11CONSTRUCTION-BUILDINGS
Jul 22, 2015School Construction Authority$289,151.50CONSTRUCTION-BUILDINGS
Jun 30, 2016Department of Transportation$284,334.05IOTB CONSTRUCTION
Jun 17, 2016Department of Cultural Affairs$263,607.00CONSTRUCTION-BUILDINGS
Sep 8, 2015Department of Environmental Protection$248,922.51IOTB CONSTRUCTION
Apr 29, 2016Department of Transportation$242,701.61CONSTRUCTION-BUILDINGS
Dec 23, 2015School Construction Authority$236,521.36CONSTRUCTION-BUILDINGS
Jul 21, 2015School Construction Authority$228,910.81CONSTRUCTION-BUILDINGS
Sep 2, 2015School Construction Authority$227,429.73CONSTRUCTION-BUILDINGS
Aug 3, 2015Department of Parks and Recreation$202,546.67IOTB CONSTRUCTION
Apr 21, 2016School Construction Authority$190,536.38CONSTRUCTION-BUILDINGS
Jun 30, 2016Department of Transportation$185,370.00IOTB CONSTRUCTION
FY 2015top 20 of 98 payments$13,962,011
DateAgencyAmountCategoryPurchase order
Mar 19, 2015School Construction Authority$736,542.44CONSTRUCTION-BUILDINGS
Sep 15, 2014School Construction Authority$723,772.94CONSTRUCTION-BUILDINGS
Sep 4, 2014Department of Transportation$704,615.00CONSTRUCTION-BUILDINGS
May 12, 2015School Construction Authority$679,778.43CONSTRUCTION-BUILDINGS
Jan 7, 2015School Construction Authority$670,517.79CONSTRUCTION-BUILDINGS
Jul 14, 2014School Construction Authority$636,469.12CONSTRUCTION-BUILDINGS
Feb 23, 2015School Construction Authority$556,028.31CONSTRUCTION-BUILDINGS
Oct 20, 2014Department of Cultural Affairs$538,262.49CONSTRUCTION-BUILDINGS
Aug 29, 2014Department of Cultural Affairs$518,494.81CONSTRUCTION-BUILDINGS
Aug 25, 2014School Construction Authority$471,146.80CONSTRUCTION-BUILDINGS
Jul 16, 2014School Construction Authority$458,802.50CONSTRUCTION-BUILDINGS
Nov 20, 2014School Construction Authority$416,436.78CONSTRUCTION-BUILDINGS
Feb 9, 2015Department of Cultural Affairs$407,661.25CONSTRUCTION-BUILDINGS
Dec 3, 2014Department of Cultural Affairs$403,916.25CONSTRUCTION-BUILDINGS
Apr 21, 2015School Construction Authority$372,933.67CONSTRUCTION-BUILDINGS
May 8, 2015Department of Transportation$369,375.00CONSTRUCTION-BUILDINGS
Jun 2, 2015School Construction Authority$351,622.74CONSTRUCTION-BUILDINGS
Jun 22, 2015School Construction Authority$351,483.38CONSTRUCTION-BUILDINGS
Jan 15, 2015School Construction Authority$320,920.45CONSTRUCTION-BUILDINGS
Oct 23, 2014School Construction Authority$317,922.25CONSTRUCTION-BUILDINGS
FY 2014top 20 of 79 payments$11,681,538
DateAgencyAmountCategoryPurchase order
Sep 27, 2013Department of Parks and Recreation$907,884.00IOTB CONSTRUCTION
Jul 5, 2013Department of Environmental Protection$776,510.58IOTB CONSTRUCTION
Jan 16, 2014Department of Cultural Affairs$594,261.84CONSTRUCTION-BUILDINGS
Aug 21, 2013Department of Environmental Protection$534,472.14IOTB CONSTRUCTION
Mar 20, 2014School Construction Authority$531,610.50CONSTRUCTION-BUILDINGS
Mar 21, 2014Department of Transportation$525,154.39CONSTRUCTION-BUILDINGS
Oct 15, 2013Department of Parks and Recreation$483,270.78IOTB CONSTRUCTION
Jun 17, 2014School Construction Authority$439,280.00CONSTRUCTION-BUILDINGS
May 15, 2014School Construction Authority$436,040.03CONSTRUCTION-BUILDINGS
Oct 15, 2013Department of Cultural Affairs$431,680.00CONSTRUCTION-BUILDINGS
Apr 16, 2014School Construction Authority$406,576.72CONSTRUCTION-BUILDINGS
Sep 5, 2013Department of Cultural Affairs$401,992.50CONSTRUCTION-BUILDINGS
May 12, 2014School Construction Authority$393,532.75CONSTRUCTION-BUILDINGS
Oct 7, 2013Department of Environmental Protection$371,405.88IOTB CONSTRUCTION
Apr 9, 2014Department of Cultural Affairs$363,694.20CONSTRUCTION-BUILDINGS
Jun 13, 2014School Construction Authority$360,900.25CONSTRUCTION-BUILDINGS
Nov 15, 2013Department of Cultural Affairs$330,920.66CONSTRUCTION-BUILDINGS
Jan 15, 2014Department of Transportation$328,081.55CONSTRUCTION-BUILDINGS
Mar 12, 2014Department of Environmental Protection$278,039.77IOTB CONSTRUCTION
Apr 10, 2014School Construction Authority$242,150.25CONSTRUCTION-BUILDINGS
FY 2013top 20 of 63 payments$7,252,123
DateAgencyAmountCategoryPurchase order
Jun 6, 2013Department of Environmental Protection$1,560,709.67IOTB CONSTRUCTION
Oct 11, 2012Department of Environmental Protection$1,099,860.72IOTB CONSTRUCTION
Mar 4, 2013Department of Environmental Protection$763,309.22IOTB CONSTRUCTION
Dec 21, 2012Department of Environmental Protection$651,510.00IOTB CONSTRUCTION
Aug 3, 2012Department of Environmental Protection$588,346.28IOTB CONSTRUCTION
Jan 24, 2013Department of Environmental Protection$560,862.20IOTB CONSTRUCTION
Aug 27, 2012Department of Environmental Protection$301,453.86IOTB CONSTRUCTION
Oct 30, 2012Department of Environmental Protection$242,562.11IOTB CONSTRUCTION
Jul 19, 2012School Construction Authority$131,536.66CONSTRUCTION-BUILDINGS
Jun 24, 2013Department of Environmental Protection$117,024.26IOTB CONSTRUCTION
Mar 15, 2013Department of Environmental Protection$108,860.50IOTB CONSTRUCTION
Apr 8, 2013School Construction Authority$102,912.29CONSTRUCTION-BUILDINGS
Dec 21, 2012Department of Environmental Protection$95,622.03IOTB CONSTRUCTION
Jan 31, 2013Department of Environmental Protection$89,822.31IOTB CONSTRUCTION
Jan 10, 2013School Construction Authority$89,490.23CONSTRUCTION-BUILDINGS
Aug 27, 2012School Construction Authority$64,807.96CONSTRUCTION-BUILDINGS
Dec 3, 2012School Construction Authority$60,015.00CONSTRUCTION-BUILDINGS
Apr 24, 2013School Construction Authority$43,873.05CONSTRUCTION-BUILDINGS
Apr 8, 2013School Construction Authority$43,003.53CONSTRUCTION-BUILDINGS
Oct 9, 2012Department of Environmental Protection$42,829.81POLLUTION REMEDIATION OBLIGATIONS
FY 2012top 20 of 167 payments$7,284,911
DateAgencyAmountCategoryPurchase order
Jun 7, 2012Department of Environmental Protection$1,814,100.24IOTB CONSTRUCTION
Sep 7, 2011School Construction Authority$572,213.02CONSTRUCTION-BUILDINGS
Aug 5, 2011School Construction Authority$391,147.30CONSTRUCTION-BUILDINGS
Mar 8, 2012School Construction Authority$272,454.89CONSTRUCTION-BUILDINGS
Apr 9, 2012Department of Environmental Protection$255,785.13IOTB CONSTRUCTION
Jul 11, 2011School Construction Authority$241,066.30CONSTRUCTION-BUILDINGS
Nov 16, 2011Department of Environmental Protection$231,464.31POLLUTION REMEDIATION OBLIGATIONS
Sep 26, 2011School Construction Authority$200,910.78CONSTRUCTION-BUILDINGS
Mar 2, 2012Department of Environmental Protection$196,774.91IOTB CONSTRUCTION
Nov 16, 2011Department of Environmental Protection$195,019.27POLLUTION REMEDIATION OBLIGATIONS
Nov 21, 2011Department of Environmental Protection$172,063.10IOTB CONSTRUCTION
Mar 20, 2012School Construction Authority$157,975.13CONSTRUCTION-BUILDINGS
Nov 16, 2011Department of Environmental Protection$151,279.23POLLUTION REMEDIATION OBLIGATIONS
Feb 1, 2012Department of Environmental Protection$134,862.57IOTB CONSTRUCTION
Aug 5, 2011School Construction Authority$124,735.00CONSTRUCTION-BUILDINGS
Dec 14, 2011School Construction Authority$124,386.82CONSTRUCTION-BUILDINGS
Oct 27, 2011School Construction Authority$122,027.03CONSTRUCTION-BUILDINGS
Apr 16, 2012School Construction Authority$98,290.80CONSTRUCTION-BUILDINGS
May 3, 2012Department of Environmental Protection$87,094.92POLLUTION REMEDIATION OBLIGATIONS
Feb 24, 2012Department of Environmental Protection$86,268.67IOTB CONSTRUCTION
FY 2011top 20 of 86 payments$5,322,346
DateAgencyAmountCategoryPurchase order
Nov 15, 2010School Construction Authority$622,687.20CONSTRUCTION-BUILDINGS
Aug 18, 2010Department of Environmental Protection$573,900.10IOTB CONSTRUCTION
May 20, 2011School Construction Authority$467,637.18CONSTRUCTION-BUILDINGS
Jan 20, 2011Department of Environmental Protection$295,747.68IOTB CONSTRUCTION
Dec 6, 2010Department of Environmental Protection$249,707.50IOTB CONSTRUCTION
Mar 29, 2011School Construction Authority$228,304.00CONSTRUCTION-BUILDINGS
Jan 11, 2011School Construction Authority$203,839.72CONSTRUCTION-BUILDINGS
Feb 17, 2011School Construction Authority$181,117.50CONSTRUCTION-BUILDINGS
May 20, 2011School Construction Authority$171,089.53CONSTRUCTION-BUILDINGS
May 19, 2011School Construction Authority$167,819.40CONSTRUCTION-BUILDINGS
May 19, 2011School Construction Authority$138,329.50CONSTRUCTION-BUILDINGS
Oct 21, 2010Department of Environmental Protection$136,068.50IOTB CONSTRUCTION
Mar 21, 2011Department of Environmental Protection$109,851.99POLLUTION REMEDIATION OBLIGATIONS
Mar 29, 2011School Construction Authority$106,938.65CONSTRUCTION-BUILDINGS
Sep 27, 2010Department of Environmental Protection$91,559.29IOTB CONSTRUCTION
Apr 7, 2011Department of Environmental Protection$88,450.36IOTB CONSTRUCTION
Oct 19, 2010School Construction Authority$74,163.51CONSTRUCTION-BUILDINGS
May 20, 2011School Construction Authority$68,541.23CONSTRUCTION-BUILDINGS
Dec 9, 2010School Construction Authority$64,733.95CONSTRUCTION-BUILDINGS
Nov 22, 2010School Construction Authority$63,240.00CONSTRUCTION-BUILDINGS
FY 2010top 20 of 68 payments$3,116,618
DateAgencyAmountCategoryPurchase order
Jan 15, 2010School Construction Authority$331,431.25CONSTRUCTION-BUILDINGS
Jun 24, 2010Department of Environmental Protection$260,723.96IOTB CONSTRUCTION
Jan 11, 2010Department of Environmental Protection$201,476.00IOTB CONSTRUCTION
Jan 25, 2010Department of Environmental Protection$185,582.50IOTB CONSTRUCTION
Apr 15, 2010School Construction Authority$182,208.10CONSTRUCTION-BUILDINGS
Feb 3, 2010School Construction Authority$171,101.18CONSTRUCTION-BUILDINGS
Feb 11, 2010Department of Environmental Protection$168,838.75IOTB CONSTRUCTION
Mar 31, 2010School Construction Authority$149,264.00CONSTRUCTION-BUILDINGS
Feb 24, 2010School Construction Authority$129,969.50CONSTRUCTION-BUILDINGS
Mar 4, 2010School Construction Authority$118,640.75CONSTRUCTION-BUILDINGS
Mar 15, 2010School Construction Authority$101,651.89CONSTRUCTION-BUILDINGS
May 14, 2010School Construction Authority$79,075.62CONSTRUCTION-BUILDINGS
Mar 26, 2010School Construction Authority$78,779.50CONSTRUCTION-BUILDINGS
Apr 26, 2010Department of Environmental Protection$77,539.00IOTB CONSTRUCTION
May 3, 2010School Construction Authority$74,671.24CONSTRUCTION-BUILDINGS
Jan 21, 2010School Construction Authority$72,125.04CONSTRUCTION-BUILDINGS
Jan 28, 2010School Construction Authority$70,504.49CONSTRUCTION-BUILDINGS
May 24, 2010Department of Environmental Protection$66,609.25IOTB CONSTRUCTION
Jan 21, 2010School Construction Authority$60,195.70CONSTRUCTION-BUILDINGS
Jan 21, 2010School Construction Authority$39,472.50CONSTRUCTION-BUILDINGS

Recent payments

DateAgencyAmountCategoryMethod
Jun 11, 2025School Construction Authority$26,754.17CONSTRUCTION-BUILDINGSCapital Contracts
Jun 11, 2025School Construction Authority$1,464.14CONSTRUCTION-BUILDINGSCapital Contracts
Jun 11, 2025School Construction Authority$143,701.51CONSTRUCTION-BUILDINGSCapital Contracts
Jun 11, 2025School Construction Authority$7,057.44CONSTRUCTION-BUILDINGSCapital Contracts
Jun 11, 2025School Construction Authority$16,197.50CONSTRUCTION-BUILDINGSCapital Contracts
Jun 11, 2025School Construction Authority$53,721.22CONSTRUCTION-BUILDINGSCapital Contracts
Jun 11, 2025School Construction Authority$181,602.00CONSTRUCTION-BUILDINGSCapital Contracts
Jun 11, 2025School Construction Authority$38,536.58CONSTRUCTION-BUILDINGSCapital Contracts
Jun 11, 2025School Construction Authority$76,950.00CONSTRUCTION-BUILDINGSCapital Contracts
Jun 10, 2025School Construction Authority$46,397.18CONSTRUCTION-BUILDINGSCapital Contracts
Jun 10, 2025School Construction Authority$40,095.00CONSTRUCTION-BUILDINGSCapital Contracts
Jun 10, 2025School Construction Authority$42,222.40CONSTRUCTION-BUILDINGSCapital Contracts
Jun 4, 2025School Construction Authority-$26,754.17CONSTRUCTION-BUILDINGSCapital Contracts
Jun 4, 2025School Construction Authority-$38,536.58CONSTRUCTION-BUILDINGSCapital Contracts
Jun 4, 2025School Construction Authority-$7,057.44CONSTRUCTION-BUILDINGSCapital Contracts
Jun 4, 2025School Construction Authority$26,754.17CONSTRUCTION-BUILDINGSCapital Contracts
Jun 4, 2025School Construction Authority$38,536.58CONSTRUCTION-BUILDINGSCapital Contracts
Jun 4, 2025School Construction Authority-$143,701.51CONSTRUCTION-BUILDINGSCapital Contracts
Jun 4, 2025School Construction Authority-$1,464.14CONSTRUCTION-BUILDINGSCapital Contracts
Jun 4, 2025School Construction Authority$1,464.14CONSTRUCTION-BUILDINGSCapital Contracts
Jun 4, 2025School Construction Authority$7,057.44CONSTRUCTION-BUILDINGSCapital Contracts
Jun 4, 2025School Construction Authority$143,701.51CONSTRUCTION-BUILDINGSCapital Contracts
May 19, 2025School Construction Authority$9,500.00CONSTRUCTION-BUILDINGSCapital Contracts
May 19, 2025School Construction Authority$141,075.00CONSTRUCTION-BUILDINGSCapital Contracts
May 19, 2025School Construction Authority$58,377.50CONSTRUCTION-BUILDINGSCapital Contracts

Other vendors serving School Construction Authority

VerifiedData refreshed Sep 7, 2026 from Checkbook NYC (checkbooknyc.com): 38,060,921 payments on record, Dec 22, 2009 to Jun 30, 2025. How we verify this data