Schiavone/Picone/Frontier- Kemper Joint Venture: New York City Government Payments

as recorded by New York City: SCHIAVONE/PICONE/FRONTIER- KEMPER JOINT VENTURE

Schiavone/Picone/Frontier- Kemper Joint Venture is the 517th-largest recipient of New York City government payments tracked by SpendLedger, and ranks 75th in IOTB CONSTRUCTION spending. Its payments amount to 0.4% of everything the Department of Environmental Protection has paid vendors in that span.

Primary spending category: IOTB CONSTRUCTION

$134,665,187total received
262payments
1agency
Jan 8, 2010Nov 13, 2017first / last payment
Follow this vendorGet an email when New York City publishes new payments to Schiavone/Picone/Frontier- Kemper Joint Venture. No spam.

Payments by fiscal year

FY 2018$441,579
FY 2017$3,731,689
FY 2016$1,342,506
FY 2015$2,667,043
FY 2014$24,271,181
FY 2013$18,994,995
FY 2012$18,821,710
FY 2011$40,424,446
FY 2010$23,970,039

Payments by fiscal year and agency

Fiscal yearAgencyPaymentsTotal
FY 2018Department of Environmental Protection27$441,579
FY 2017Department of Environmental Protection33$3,731,689
FY 2016Department of Environmental Protection5$1,342,506
FY 2015Department of Environmental Protection25$2,667,043
FY 2014Department of Environmental Protection33$24,271,181
FY 2013Department of Environmental Protection44$18,994,995
FY 2012Department of Environmental Protection38$18,821,710
FY 2011Department of Environmental Protection44$40,424,446
FY 2010Department of Environmental Protection13$23,970,039
Total262$134,665,187

What the payments were for

Spending categories exactly as New York City government codes them in its own accounting; we do not reclassify.

CategoryPaymentsTotalFirst / last
IOTB CONSTRUCTION262$134,665,187Jan 8, 2010 Nov 13, 2017

Largest payments by fiscal year

The biggest individual payments in each fiscal year, up to 20 per year. Where the source publishes a purchase order behind a payment, the PO description appears; older payments may carry a bare PO reference because the government's published PO files do not reach back that far.

Download this table as CSV (free, with source citation on every row)

FY 2018top 20 of 27 payments$441,579
DateAgencyAmountCategoryPurchase order
Nov 2, 2017Department of Environmental Protection$157,811.79IOTB CONSTRUCTION
Nov 8, 2017Department of Environmental Protection$157,811.79IOTB CONSTRUCTION
Nov 6, 2017Department of Environmental Protection$138,960.22IOTB CONSTRUCTION
Nov 13, 2017Department of Environmental Protection$138,960.22IOTB CONSTRUCTION
Nov 2, 2017Department of Environmental Protection$102,188.22IOTB CONSTRUCTION
Nov 8, 2017Department of Environmental Protection$102,188.22IOTB CONSTRUCTION
Nov 13, 2017Department of Environmental Protection$14,579.29IOTB CONSTRUCTION
Nov 6, 2017Department of Environmental Protection$14,579.29IOTB CONSTRUCTION
Nov 6, 2017Department of Environmental Protection$11,412.64IOTB CONSTRUCTION
Nov 13, 2017Department of Environmental Protection$11,412.64IOTB CONSTRUCTION
Nov 13, 2017Department of Environmental Protection$6,659.92IOTB CONSTRUCTION
Nov 6, 2017Department of Environmental Protection$6,659.92IOTB CONSTRUCTION
Nov 13, 2017Department of Environmental Protection$4,109.59IOTB CONSTRUCTION
Nov 6, 2017Department of Environmental Protection$4,109.59IOTB CONSTRUCTION
Nov 13, 2017Department of Environmental Protection$3,010.34IOTB CONSTRUCTION
Nov 6, 2017Department of Environmental Protection$3,010.34IOTB CONSTRUCTION
Nov 13, 2017Department of Environmental Protection$2,847.21IOTB CONSTRUCTION
Nov 6, 2017Department of Environmental Protection$2,847.21IOTB CONSTRUCTION
Nov 6, 2017Department of Environmental Protection-$2,847.21IOTB CONSTRUCTION
Nov 6, 2017Department of Environmental Protection-$3,010.34IOTB CONSTRUCTION
FY 2017top 20 of 33 payments$3,731,689
DateAgencyAmountCategoryPurchase order
Nov 9, 2016Department of Environmental Protection$1,066,563.37IOTB CONSTRUCTION
Aug 8, 2016Department of Environmental Protection$952,476.30IOTB CONSTRUCTION
Nov 14, 2016Department of Environmental Protection$196,954.75IOTB CONSTRUCTION
Nov 14, 2016Department of Environmental Protection$196,012.98IOTB CONSTRUCTION
Nov 14, 2016Department of Environmental Protection$150,300.00IOTB CONSTRUCTION
Nov 14, 2016Department of Environmental Protection$147,690.00IOTB CONSTRUCTION
Nov 14, 2016Department of Environmental Protection$107,039.51IOTB CONSTRUCTION
Nov 14, 2016Department of Environmental Protection$91,261.58IOTB CONSTRUCTION
Nov 14, 2016Department of Environmental Protection$85,347.13IOTB CONSTRUCTION
Nov 14, 2016Department of Environmental Protection$78,373.94IOTB CONSTRUCTION
Nov 14, 2016Department of Environmental Protection$70,794.67IOTB CONSTRUCTION
Nov 14, 2016Department of Environmental Protection$61,844.26IOTB CONSTRUCTION
Feb 27, 2017Department of Environmental Protection$54,440.08IOTB CONSTRUCTION
Nov 14, 2016Department of Environmental Protection$50,130.33IOTB CONSTRUCTION
Nov 14, 2016Department of Environmental Protection$45,323.03IOTB CONSTRUCTION
Feb 27, 2017Department of Environmental Protection$41,244.18IOTB CONSTRUCTION
Nov 14, 2016Department of Environmental Protection$41,054.20IOTB CONSTRUCTION
Nov 14, 2016Department of Environmental Protection$31,681.21IOTB CONSTRUCTION
Nov 14, 2016Department of Environmental Protection$30,886.83IOTB CONSTRUCTION
Feb 27, 2017Department of Environmental Protection$30,854.17IOTB CONSTRUCTION
FY 2016top 5 of 5 payments$1,342,506
DateAgencyAmountCategoryPurchase order
Oct 9, 2015Department of Environmental Protection$1,140,000.00IOTB CONSTRUCTION
Oct 9, 2015Department of Environmental Protection$124,423.30IOTB CONSTRUCTION
Mar 7, 2016Department of Environmental Protection$31,814.93IOTB CONSTRUCTION
Mar 7, 2016Department of Environmental Protection$28,732.41IOTB CONSTRUCTION
Mar 7, 2016Department of Environmental Protection$17,534.95IOTB CONSTRUCTION
FY 2015top 20 of 25 payments$2,667,043
DateAgencyAmountCategoryPurchase order
Nov 24, 2014Department of Environmental Protection$638,260.00IOTB CONSTRUCTION
Mar 2, 2015Department of Environmental Protection$388,490.95IOTB CONSTRUCTION
Nov 24, 2014Department of Environmental Protection$340,720.45IOTB CONSTRUCTION
Nov 10, 2014Department of Environmental Protection$256,134.08IOTB CONSTRUCTION
Mar 2, 2015Department of Environmental Protection$214,686.15IOTB CONSTRUCTION
Nov 10, 2014Department of Environmental Protection$170,015.51IOTB CONSTRUCTION
Mar 2, 2015Department of Environmental Protection$140,359.00IOTB CONSTRUCTION
Mar 2, 2015Department of Environmental Protection$101,996.00IOTB CONSTRUCTION
Mar 4, 2015Department of Environmental Protection$79,693.50IOTB CONSTRUCTION
Mar 2, 2015Department of Environmental Protection$61,713.82IOTB CONSTRUCTION
Mar 4, 2015Department of Environmental Protection$53,290.83IOTB CONSTRUCTION
Aug 29, 2014Department of Environmental Protection$49,504.61IOTB CONSTRUCTION
Nov 10, 2014Department of Environmental Protection$27,750.08IOTB CONSTRUCTION
Mar 4, 2015Department of Environmental Protection$27,254.50IOTB CONSTRUCTION
Mar 4, 2015Department of Environmental Protection$22,971.88IOTB CONSTRUCTION
Mar 2, 2015Department of Environmental Protection$22,478.94IOTB CONSTRUCTION
Mar 4, 2015Department of Environmental Protection$16,640.02IOTB CONSTRUCTION
Mar 4, 2015Department of Environmental Protection$13,480.74IOTB CONSTRUCTION
Mar 4, 2015Department of Environmental Protection$11,251.07IOTB CONSTRUCTION
Mar 4, 2015Department of Environmental Protection$8,948.18IOTB CONSTRUCTION
FY 2014top 20 of 33 payments$24,271,181
DateAgencyAmountCategoryPurchase order
Jan 28, 2014Department of Environmental Protection$6,364,490.87IOTB CONSTRUCTION
Aug 12, 2013Department of Environmental Protection$3,742,140.26IOTB CONSTRUCTION
Feb 24, 2014Department of Environmental Protection$2,297,046.96IOTB CONSTRUCTION
Oct 15, 2013Department of Environmental Protection$1,753,330.20IOTB CONSTRUCTION
Sep 16, 2013Department of Environmental Protection$1,676,872.11IOTB CONSTRUCTION
Jul 3, 2013Department of Environmental Protection$1,538,599.65IOTB CONSTRUCTION
May 12, 2014Department of Environmental Protection$1,345,098.79IOTB CONSTRUCTION
Jul 17, 2013Department of Environmental Protection$1,093,060.00IOTB CONSTRUCTION
Dec 16, 2013Department of Environmental Protection$917,185.82IOTB CONSTRUCTION
Dec 23, 2013Department of Environmental Protection$847,797.50IOTB CONSTRUCTION
Apr 8, 2014Department of Environmental Protection$601,942.99IOTB CONSTRUCTION
Mar 24, 2014Department of Environmental Protection$474,382.50IOTB CONSTRUCTION
Mar 7, 2014Department of Environmental Protection$296,590.50IOTB CONSTRUCTION
Feb 26, 2014Department of Environmental Protection$220,181.43IOTB CONSTRUCTION
Jul 16, 2013Department of Environmental Protection$177,431.20IOTB CONSTRUCTION
Mar 7, 2014Department of Environmental Protection$119,224.09IOTB CONSTRUCTION
Jun 23, 2014Department of Environmental Protection$117,050.00IOTB CONSTRUCTION
Dec 9, 2013Department of Environmental Protection$107,167.17IOTB CONSTRUCTION
Apr 14, 2014Department of Environmental Protection$93,658.57IOTB CONSTRUCTION
Dec 9, 2013Department of Environmental Protection$74,668.67IOTB CONSTRUCTION
FY 2013top 20 of 44 payments$18,994,995
DateAgencyAmountCategoryPurchase order
Jul 16, 2012Department of Environmental Protection$4,853,588.35IOTB CONSTRUCTION
Dec 13, 2012Department of Environmental Protection$1,982,299.50IOTB CONSTRUCTION
Apr 3, 2013Department of Environmental Protection$1,784,535.87IOTB CONSTRUCTION
Sep 14, 2012Department of Environmental Protection$1,762,007.02IOTB CONSTRUCTION
Jan 4, 2013Department of Environmental Protection$1,542,076.50IOTB CONSTRUCTION
Apr 22, 2013Department of Environmental Protection$1,489,104.91IOTB CONSTRUCTION
Oct 30, 2012Department of Environmental Protection$677,332.50IOTB CONSTRUCTION
Mar 26, 2013Department of Environmental Protection$592,022.79IOTB CONSTRUCTION
Feb 7, 2013Department of Environmental Protection$590,769.68IOTB CONSTRUCTION
Nov 9, 2012Department of Environmental Protection$521,755.50IOTB CONSTRUCTION
Jul 6, 2012Department of Environmental Protection$477,258.66IOTB CONSTRUCTION
Aug 23, 2012Department of Environmental Protection$336,303.96IOTB CONSTRUCTION
Jun 21, 2013Department of Environmental Protection$304,117.33IOTB CONSTRUCTION
Oct 30, 2012Department of Environmental Protection$289,000.00IOTB CONSTRUCTION
Jun 24, 2013Department of Environmental Protection$260,452.98IOTB CONSTRUCTION
Oct 9, 2012Department of Environmental Protection$213,770.38IOTB CONSTRUCTION
Nov 7, 2012Department of Environmental Protection$167,514.73IOTB CONSTRUCTION
Jul 6, 2012Department of Environmental Protection$99,570.02IOTB CONSTRUCTION
Oct 30, 2012Department of Environmental Protection$96,082.45IOTB CONSTRUCTION
Jul 6, 2012Department of Environmental Protection$90,833.98IOTB CONSTRUCTION
FY 2012top 20 of 38 payments$18,821,710
DateAgencyAmountCategoryPurchase order
May 23, 2012Department of Environmental Protection$6,637,069.21IOTB CONSTRUCTION
Mar 9, 2012Department of Environmental Protection$1,258,599.38IOTB CONSTRUCTION
Sep 8, 2011Department of Environmental Protection$1,238,990.00IOTB CONSTRUCTION
Apr 27, 2012Department of Environmental Protection$1,043,254.78IOTB CONSTRUCTION
Aug 8, 2011Department of Environmental Protection$988,858.32IOTB CONSTRUCTION
Nov 14, 2011Department of Environmental Protection$831,926.97IOTB CONSTRUCTION
Feb 6, 2012Department of Environmental Protection$725,099.92IOTB CONSTRUCTION
Nov 16, 2011Department of Environmental Protection$652,720.08IOTB CONSTRUCTION
Aug 18, 2011Department of Environmental Protection$608,336.71IOTB CONSTRUCTION
Apr 30, 2012Department of Environmental Protection$530,156.20IOTB CONSTRUCTION
Oct 24, 2011Department of Environmental Protection$493,227.64IOTB CONSTRUCTION
Feb 15, 2012Department of Environmental Protection$481,873.53IOTB CONSTRUCTION
Aug 18, 2011Department of Environmental Protection$438,959.07IOTB CONSTRUCTION
Nov 16, 2011Department of Environmental Protection$390,107.22IOTB CONSTRUCTION
Jul 25, 2011Department of Environmental Protection$290,348.50IOTB CONSTRUCTION
Nov 16, 2011Department of Environmental Protection$284,126.51IOTB CONSTRUCTION
Nov 16, 2011Department of Environmental Protection$274,443.90IOTB CONSTRUCTION
Apr 11, 2012Department of Environmental Protection$218,191.25IOTB CONSTRUCTION
Nov 17, 2011Department of Environmental Protection$216,735.33IOTB CONSTRUCTION
May 24, 2012Department of Environmental Protection$159,600.00IOTB CONSTRUCTION
FY 2011top 20 of 44 payments$40,424,446
DateAgencyAmountCategoryPurchase order
Mar 11, 2011Department of Environmental Protection$12,569,187.15IOTB CONSTRUCTION
Sep 20, 2010Department of Environmental Protection$7,056,818.83IOTB CONSTRUCTION
Jan 24, 2011Department of Environmental Protection$5,491,000.00IOTB CONSTRUCTION
Nov 1, 2010Department of Environmental Protection$2,299,541.50IOTB CONSTRUCTION
Aug 26, 2010Department of Environmental Protection$1,891,830.00IOTB CONSTRUCTION
Jan 31, 2011Department of Environmental Protection$1,825,566.55IOTB CONSTRUCTION
Jul 29, 2010Department of Environmental Protection$1,725,846.00IOTB CONSTRUCTION
Jul 22, 2010Department of Environmental Protection$1,203,719.34IOTB CONSTRUCTION
Sep 7, 2010Department of Environmental Protection$1,073,207.53IOTB CONSTRUCTION
Jul 23, 2010Department of Environmental Protection$929,661.40IOTB CONSTRUCTION
Apr 15, 2011Department of Environmental Protection$904,632.29IOTB CONSTRUCTION
Dec 8, 2010Department of Environmental Protection$469,680.06IOTB CONSTRUCTION
Nov 9, 2010Department of Environmental Protection$361,130.13IOTB CONSTRUCTION
Nov 9, 2010Department of Environmental Protection$325,149.98IOTB CONSTRUCTION
Sep 7, 2010Department of Environmental Protection$271,284.42IOTB CONSTRUCTION
Nov 5, 2010Department of Environmental Protection$200,580.13IOTB CONSTRUCTION
Nov 9, 2010Department of Environmental Protection$194,639.52IOTB CONSTRUCTION
Dec 27, 2010Department of Environmental Protection$162,224.69IOTB CONSTRUCTION
Nov 9, 2010Department of Environmental Protection$153,039.94IOTB CONSTRUCTION
Nov 9, 2010Department of Environmental Protection$146,346.85IOTB CONSTRUCTION
FY 2010top 13 of 13 payments$23,970,039
DateAgencyAmountCategoryPurchase order
Feb 16, 2010Department of Environmental Protection$6,177,850.00IOTB CONSTRUCTION
May 20, 2010Department of Environmental Protection$5,410,409.50IOTB CONSTRUCTION
Apr 23, 2010Department of Environmental Protection$3,698,150.48IOTB CONSTRUCTION
Jun 21, 2010Department of Environmental Protection$2,470,611.15IOTB CONSTRUCTION
Mar 3, 2010Department of Environmental Protection$1,670,741.95IOTB CONSTRUCTION
Jun 21, 2010Department of Environmental Protection$1,447,083.81IOTB CONSTRUCTION
Apr 15, 2010Department of Environmental Protection$1,058,228.75IOTB CONSTRUCTION
Jan 8, 2010Department of Environmental Protection$804,284.01IOTB CONSTRUCTION
Jun 21, 2010Department of Environmental Protection$533,332.58IOTB CONSTRUCTION
Jun 21, 2010Department of Environmental Protection$333,099.36IOTB CONSTRUCTION
Apr 23, 2010Department of Environmental Protection$288,432.54IOTB CONSTRUCTION
Apr 23, 2010Department of Environmental Protection$58,584.12IOTB CONSTRUCTION
Apr 23, 2010Department of Environmental Protection$19,230.47IOTB CONSTRUCTION

Recent payments

DateAgencyAmountCategoryMethod
Nov 13, 2017Department of Environmental Protection$3,010.34IOTB CONSTRUCTIONCapital Contracts
Nov 13, 2017Department of Environmental Protection$2,847.21IOTB CONSTRUCTIONCapital Contracts
Nov 13, 2017Department of Environmental Protection$14,579.29IOTB CONSTRUCTIONCapital Contracts
Nov 13, 2017Department of Environmental Protection$6,659.92IOTB CONSTRUCTIONCapital Contracts
Nov 13, 2017Department of Environmental Protection$4,109.59IOTB CONSTRUCTIONCapital Contracts
Nov 13, 2017Department of Environmental Protection$11,412.64IOTB CONSTRUCTIONCapital Contracts
Nov 13, 2017Department of Environmental Protection$138,960.22IOTB CONSTRUCTIONCapital Contracts
Nov 8, 2017Department of Environmental Protection$157,811.79IOTB CONSTRUCTIONCapital Contracts
Nov 8, 2017Department of Environmental Protection$102,188.22IOTB CONSTRUCTIONCapital Contracts
Nov 6, 2017Department of Environmental Protection$3,010.34IOTB CONSTRUCTIONCapital Contracts
Nov 6, 2017Department of Environmental Protection-$2,847.21IOTB CONSTRUCTIONCapital Contracts
Nov 6, 2017Department of Environmental Protection-$3,010.34IOTB CONSTRUCTIONCapital Contracts
Nov 6, 2017Department of Environmental Protection$138,960.22IOTB CONSTRUCTIONCapital Contracts
Nov 6, 2017Department of Environmental Protection-$11,412.64IOTB CONSTRUCTIONCapital Contracts
Nov 6, 2017Department of Environmental Protection-$6,659.92IOTB CONSTRUCTIONCapital Contracts
Nov 6, 2017Department of Environmental Protection-$4,109.59IOTB CONSTRUCTIONCapital Contracts
Nov 6, 2017Department of Environmental Protection$11,412.64IOTB CONSTRUCTIONCapital Contracts
Nov 6, 2017Department of Environmental Protection-$138,960.22IOTB CONSTRUCTIONCapital Contracts
Nov 6, 2017Department of Environmental Protection$6,659.92IOTB CONSTRUCTIONCapital Contracts
Nov 6, 2017Department of Environmental Protection$2,847.21IOTB CONSTRUCTIONCapital Contracts
Nov 6, 2017Department of Environmental Protection-$14,579.29IOTB CONSTRUCTIONCapital Contracts
Nov 6, 2017Department of Environmental Protection$14,579.29IOTB CONSTRUCTIONCapital Contracts
Nov 6, 2017Department of Environmental Protection$4,109.59IOTB CONSTRUCTIONCapital Contracts
Nov 2, 2017Department of Environmental Protection-$157,811.79IOTB CONSTRUCTIONCapital Contracts
Nov 2, 2017Department of Environmental Protection$157,811.79IOTB CONSTRUCTIONCapital Contracts

Other vendors serving Department of Environmental Protection

VerifiedData refreshed Sep 7, 2026 from Checkbook NYC (checkbooknyc.com): 38,060,921 payments on record, Dec 22, 2009 to Jun 30, 2025. How we verify this data