Tutor Perini Corporation: New York City Government Payments

as recorded by New York City: TUTOR PERINI CORPORATION

Tutor Perini Corporation is the 57th-largest recipient of New York City government payments tracked by SpendLedger, and ranks first in DESIGN-BUILD: BUILDINGS spending. Its payments amount to 16% of everything the Department of Correction has paid vendors in that span. Payments to it rose 232.3% year over year.

Primary spending category: DESIGN-BUILD: BUILDINGS

$990,714,726total received
684payments
4agencies
Feb 21, 2013Jun 30, 2025first / last payment
Follow this vendorGet an email when New York City publishes new payments to Tutor Perini Corporation. No spam.

Payments by fiscal year

FY 2025$573,014,628
FY 2024$172,437,865
FY 2023$5,483,366
FY 2022$9,240,419
FY 2021$12,137,879
FY 2020$8,787,534
FY 2019$8,757,497
FY 2018$21,565,866
FY 2017$34,150,031
FY 2016$17,953,563
FY 2015$11,857,414
FY 2014$27,730,567
FY 2013$87,598,095

Payments by fiscal year and agency

Fiscal yearAgencyPaymentsTotal
FY 2025Department of Correction37$563,219,254
FY 2025Department of Transportation139$9,795,374
FY 2024Department of Correction12$168,294,933
FY 2024Department of Transportation60$4,142,932
FY 2023Department of Transportation45$5,483,366
FY 2022Department of Transportation36$9,240,419
FY 2021Department of Transportation55$12,137,879
FY 2020Department of Transportation68$8,787,534
FY 2019Department of Transportation57$8,757,497
FY 2018Department of Transportation39$19,529,493
FY 2018Miscellaneous3$2,036,373
FY 2017Department of Transportation37$34,150,031
FY 2016Department of Transportation44$17,953,563
FY 2015Department of Transportation22$10,309,883
FY 2015Department of Environmental Protection3$1,547,531
FY 2014Department of Environmental Protection10$22,328,441
FY 2014Department of Transportation12$5,402,126
FY 2013Department of Environmental Protection5$87,598,095
Total684$990,714,726

What the payments were for

Spending categories exactly as New York City government codes them in its own accounting; we do not reclassify.

CategoryPaymentsTotalFirst / last
DESIGN-BUILD: BUILDINGS46$581,190,798Aug 7, 2023 Jun 30, 2025
MAINT & REP GENERAL1$5,418Feb 11, 2019 Feb 11, 2019
JUDGMENTS AND CLAIMS-INTEREST1$476,263Oct 12, 2017 Oct 12, 2017
PROMPT PAYMENT INTEREST6$276Aug 17, 2020 Nov 25, 2020
JUDGMENTS AND CLAIMS-NOT REPORTABLE2$1,560,110Oct 10, 2017 May 10, 2018
POLLUTION REMEDIATION OBLIGATIONS DESIGN-BUILD: BUILDINGS3$150,323,389May 8, 2025 Jun 30, 2025
IOTB CONSTRUCTION607$145,684,403Feb 26, 2014 Jun 24, 2025
CONTRACTUAL SERVICES GENERAL18$111,474,068Feb 21, 2013 Apr 24, 2015

Largest payments by fiscal year

The biggest individual payments in each fiscal year, up to 20 per year. Where the source publishes a purchase order behind a payment, the PO description appears; older payments may carry a bare PO reference because the government's published PO files do not reach back that far.

Download this table as CSV (free, with source citation on every row)

FY 2025top 20 of 176 payments$573,014,628
DateAgencyAmountCategoryPurchase order
Dec 2, 2024Department of Correction$99,999,999.00DESIGN-BUILD: BUILDINGS
Apr 8, 2025Department of Correction$88,909,602.58DESIGN-BUILD: BUILDINGS
May 8, 2025Department of Correction$80,975,225.68POLLUTION REMEDIATION OBLIGATIONS DESIGN-BUILD: BUILDINGS
Feb 24, 2025Department of Correction$36,302,003.55DESIGN-BUILD: BUILDINGS
Jun 5, 2025Department of Correction$34,921,344.43POLLUTION REMEDIATION OBLIGATIONS DESIGN-BUILD: BUILDINGS
Jun 30, 2025Department of Correction$34,426,818.87POLLUTION REMEDIATION OBLIGATIONS DESIGN-BUILD: BUILDINGS
Sep 17, 2024Department of Correction$33,801,686.08DESIGN-BUILD: BUILDINGS
Jan 2, 2025Department of Correction$20,196,253.34DESIGN-BUILD: BUILDINGS
Nov 19, 2024Department of Correction$19,834,562.82DESIGN-BUILD: BUILDINGS
Mar 14, 2025Department of Correction$19,536,173.06DESIGN-BUILD: BUILDINGS
Oct 28, 2024Department of Correction$18,584,455.44DESIGN-BUILD: BUILDINGS
May 8, 2025Department of Correction$17,637,513.20DESIGN-BUILD: BUILDINGS
Apr 8, 2025Department of Correction$12,874,934.97DESIGN-BUILD: BUILDINGS
Dec 2, 2024Department of Correction$11,647,501.00DESIGN-BUILD: BUILDINGS
Jul 17, 2024Department of Correction$10,409,016.58DESIGN-BUILD: BUILDINGS
Aug 12, 2024Department of Correction$9,825,820.59DESIGN-BUILD: BUILDINGS
Feb 3, 2025Department of Correction$3,302,635.70DESIGN-BUILD: BUILDINGS
Sep 4, 2024Department of Correction$2,289,798.25DESIGN-BUILD: BUILDINGS
Jun 16, 2025Department of Correction$1,411,611.40DESIGN-BUILD: BUILDINGS
Sep 4, 2024Department of Correction$1,392,565.20DESIGN-BUILD: BUILDINGS
FY 2024top 20 of 72 payments$172,437,865
DateAgencyAmountCategoryPurchase order
Aug 7, 2023Department of Correction$61,838,224.00DESIGN-BUILD: BUILDINGS
Sep 6, 2023Department of Correction$45,150,614.95DESIGN-BUILD: BUILDINGS
May 7, 2024Department of Correction$9,280,927.31DESIGN-BUILD: BUILDINGS
Dec 12, 2023Department of Correction$9,244,239.21DESIGN-BUILD: BUILDINGS
Apr 1, 2024Department of Correction$8,256,006.55DESIGN-BUILD: BUILDINGS
Mar 4, 2024Department of Correction$6,510,989.35DESIGN-BUILD: BUILDINGS
Feb 7, 2024Department of Correction$6,456,276.95DESIGN-BUILD: BUILDINGS
Jun 13, 2024Department of Correction$6,008,583.95DESIGN-BUILD: BUILDINGS
Jan 22, 2024Department of Correction$5,870,650.30DESIGN-BUILD: BUILDINGS
Nov 6, 2023Department of Correction$5,467,386.09DESIGN-BUILD: BUILDINGS
Jun 13, 2024Department of Correction$2,603,599.63DESIGN-BUILD: BUILDINGS
Sep 11, 2023Department of Correction$1,607,434.80DESIGN-BUILD: BUILDINGS
Dec 26, 2023Department of Transportation$590,380.52IOTB CONSTRUCTION
Sep 18, 2023Department of Transportation$345,780.30IOTB CONSTRUCTION
Jan 8, 2024Department of Transportation$279,415.60IOTB CONSTRUCTION
Jan 11, 2024Department of Transportation$238,381.09IOTB CONSTRUCTION
Aug 15, 2023Department of Transportation$227,048.94IOTB CONSTRUCTION
Jun 20, 2024Department of Transportation$201,292.14IOTB CONSTRUCTION
Sep 13, 2023Department of Transportation$200,853.44IOTB CONSTRUCTION
Feb 14, 2024Department of Transportation$198,816.00IOTB CONSTRUCTION
FY 2023top 20 of 45 payments$5,483,366
DateAgencyAmountCategoryPurchase order
Dec 12, 2022Department of Transportation$551,170.40IOTB CONSTRUCTION
Nov 14, 2022Department of Transportation$523,064.93IOTB CONSTRUCTION
Mar 30, 2023Department of Transportation$518,260.80IOTB CONSTRUCTION
Jul 11, 2022Department of Transportation$472,383.55IOTB CONSTRUCTION
Aug 3, 2022Department of Transportation$460,061.19IOTB CONSTRUCTION
Feb 21, 2023Department of Transportation$457,787.20IOTB CONSTRUCTION
Jan 30, 2023Department of Transportation$392,395.31IOTB CONSTRUCTION
Oct 11, 2022Department of Transportation$350,997.52IOTB CONSTRUCTION
Apr 12, 2023Department of Transportation$183,674.96IOTB CONSTRUCTION
Aug 29, 2022Department of Transportation$163,114.00IOTB CONSTRUCTION
Feb 9, 2023Department of Transportation$133,780.61IOTB CONSTRUCTION
Jun 14, 2023Department of Transportation$119,740.30IOTB CONSTRUCTION
Dec 12, 2022Department of Transportation$103,344.45IOTB CONSTRUCTION
Nov 14, 2022Department of Transportation$98,074.68IOTB CONSTRUCTION
Mar 30, 2023Department of Transportation$97,173.90IOTB CONSTRUCTION
Jul 11, 2022Department of Transportation$88,571.91IOTB CONSTRUCTION
Aug 3, 2022Department of Transportation$86,261.48IOTB CONSTRUCTION
Feb 21, 2023Department of Transportation$85,835.10IOTB CONSTRUCTION
Jan 30, 2023Department of Transportation$73,574.12IOTB CONSTRUCTION
Oct 11, 2022Department of Transportation$65,812.03IOTB CONSTRUCTION
FY 2022top 20 of 36 payments$9,240,419
DateAgencyAmountCategoryPurchase order
Jul 12, 2021Department of Transportation$1,017,922.34IOTB CONSTRUCTION
Sep 7, 2021Department of Transportation$823,973.15IOTB CONSTRUCTION
Aug 2, 2021Department of Transportation$781,128.43IOTB CONSTRUCTION
Dec 20, 2021Department of Transportation$750,194.40IOTB CONSTRUCTION
Nov 3, 2021Department of Transportation$701,709.48IOTB CONSTRUCTION
Oct 5, 2021Department of Transportation$691,795.28IOTB CONSTRUCTION
Jan 7, 2022Department of Transportation$640,449.64IOTB CONSTRUCTION
May 9, 2022Department of Transportation$546,012.75IOTB CONSTRUCTION
Apr 13, 2022Department of Transportation$489,266.40IOTB CONSTRUCTION
Mar 7, 2022Department of Transportation$361,607.82IOTB CONSTRUCTION
Feb 7, 2022Department of Transportation$275,759.27IOTB CONSTRUCTION
Jun 8, 2022Department of Transportation$252,500.00IOTB CONSTRUCTION
Jul 12, 2021Department of Transportation$190,860.44IOTB CONSTRUCTION
Sep 7, 2021Department of Transportation$154,494.97IOTB CONSTRUCTION
Aug 2, 2021Department of Transportation$146,461.58IOTB CONSTRUCTION
Dec 20, 2021Department of Transportation$140,661.45IOTB CONSTRUCTION
Nov 3, 2021Department of Transportation$131,570.53IOTB CONSTRUCTION
Oct 5, 2021Department of Transportation$129,711.62IOTB CONSTRUCTION
Jan 7, 2022Department of Transportation$120,084.31IOTB CONSTRUCTION
Oct 5, 2021Department of Transportation$118,257.20IOTB CONSTRUCTION
FY 2021top 20 of 55 payments$12,137,879
DateAgencyAmountCategoryPurchase order
May 10, 2021Department of Transportation$2,448,089.68IOTB CONSTRUCTION
Apr 14, 2021Department of Transportation$1,718,616.00IOTB CONSTRUCTION
Mar 18, 2021Department of Transportation$1,588,421.20IOTB CONSTRUCTION
Jun 8, 2021Department of Transportation$1,037,792.27IOTB CONSTRUCTION
Feb 25, 2021Department of Transportation$864,974.56IOTB CONSTRUCTION
Aug 12, 2020Department of Transportation$489,527.12IOTB CONSTRUCTION
May 10, 2021Department of Transportation$459,016.82IOTB CONSTRUCTION
Jan 29, 2021Department of Transportation$362,397.28IOTB CONSTRUCTION
Apr 14, 2021Department of Transportation$322,240.50IOTB CONSTRUCTION
Mar 18, 2021Department of Transportation$297,828.97IOTB CONSTRUCTION
Dec 16, 2020Department of Transportation$233,142.64IOTB CONSTRUCTION
Jun 8, 2021Department of Transportation$194,586.05IOTB CONSTRUCTION
Feb 25, 2021Department of Transportation$162,182.73IOTB CONSTRUCTION
Sep 15, 2020Department of Transportation$155,922.92IOTB CONSTRUCTION
Jul 28, 2020Department of Transportation$155,197.03IOTB CONSTRUCTION
May 10, 2021Department of Transportation$153,005.60IOTB CONSTRUCTION
Nov 17, 2020Department of Transportation$151,665.83IOTB CONSTRUCTION
Aug 13, 2020Department of Transportation$150,479.44IOTB CONSTRUCTION
Nov 5, 2020Department of Transportation$150,340.23IOTB CONSTRUCTION
Nov 5, 2020Department of Transportation$138,483.43IOTB CONSTRUCTION
FY 2020top 20 of 68 payments$8,787,534
DateAgencyAmountCategoryPurchase order
Mar 9, 2020Department of Transportation$1,560,000.00IOTB CONSTRUCTION
Feb 12, 2020Department of Transportation$625,260.00IOTB CONSTRUCTION
Jan 22, 2020Department of Transportation$571,584.56IOTB CONSTRUCTION
Sep 23, 2019Department of Transportation$466,255.43IOTB CONSTRUCTION
Dec 31, 2019Department of Transportation$448,000.00IOTB CONSTRUCTION
Jul 15, 2019Department of Transportation$415,788.19IOTB CONSTRUCTION
Oct 21, 2019Department of Transportation$343,422.00IOTB CONSTRUCTION
Mar 2, 2020Department of Transportation$294,162.27IOTB CONSTRUCTION
Mar 9, 2020Department of Transportation$292,500.00IOTB CONSTRUCTION
Oct 21, 2019Department of Transportation$285,125.90IOTB CONSTRUCTION
Jun 4, 2020Department of Transportation$278,603.44IOTB CONSTRUCTION
Jul 2, 2019Department of Transportation$223,678.80IOTB CONSTRUCTION
Sep 9, 2019Department of Transportation$219,479.90IOTB CONSTRUCTION
Dec 9, 2019Department of Transportation$207,640.40IOTB CONSTRUCTION
Jul 15, 2019Department of Transportation$202,551.34IOTB CONSTRUCTION
Oct 21, 2019Department of Transportation$197,950.52IOTB CONSTRUCTION
Nov 6, 2019Department of Transportation$166,718.80IOTB CONSTRUCTION
Feb 5, 2020Department of Transportation$155,882.63IOTB CONSTRUCTION
Dec 10, 2019Department of Transportation$129,227.69IOTB CONSTRUCTION
Dec 31, 2019Department of Transportation$120,838.96IOTB CONSTRUCTION
FY 2019top 20 of 57 payments$8,757,497
DateAgencyAmountCategoryPurchase order
Dec 17, 2018Department of Transportation$2,623,551.09IOTB CONSTRUCTION
May 28, 2019Department of Transportation$616,437.01IOTB CONSTRUCTION
Aug 13, 2018Department of Transportation$602,358.36IOTB CONSTRUCTION
Nov 19, 2018Department of Transportation$540,879.12IOTB CONSTRUCTION
Dec 17, 2018Department of Transportation$491,915.83IOTB CONSTRUCTION
Jun 19, 2019Department of Transportation$476,010.56IOTB CONSTRUCTION
Aug 27, 2018Department of Transportation$420,675.46IOTB CONSTRUCTION
Jul 16, 2018Department of Transportation$312,183.23IOTB CONSTRUCTION
Sep 24, 2018Department of Transportation$297,776.48IOTB CONSTRUCTION
May 20, 2019Department of Transportation$284,529.19IOTB CONSTRUCTION
Jul 1, 2018Department of Transportation$283,888.45IOTB CONSTRUCTION
Dec 17, 2018Department of Transportation$184,244.93IOTB CONSTRUCTION
May 22, 2019Department of Transportation$118,497.51IOTB CONSTRUCTION
May 20, 2019Department of Transportation$118,404.98IOTB CONSTRUCTION
May 28, 2019Department of Transportation$115,581.94IOTB CONSTRUCTION
Aug 13, 2018Department of Transportation$109,826.32IOTB CONSTRUCTION
Aug 27, 2018Department of Transportation$105,168.87IOTB CONSTRUCTION
Nov 19, 2018Department of Transportation$101,309.84IOTB CONSTRUCTION
Jun 19, 2019Department of Transportation$89,251.98IOTB CONSTRUCTION
May 22, 2019Department of Transportation$77,689.60IOTB CONSTRUCTION
FY 2018top 20 of 42 payments$21,565,866
DateAgencyAmountCategoryPurchase order
Dec 11, 2017Department of Transportation$3,560,043.70IOTB CONSTRUCTION
Aug 9, 2017Department of Transportation$3,397,330.45IOTB CONSTRUCTION
Jan 16, 2018Department of Transportation$1,730,997.74IOTB CONSTRUCTION
Oct 3, 2017Department of Transportation$1,620,070.46IOTB CONSTRUCTION
Jul 12, 2017Department of Transportation$1,263,567.78IOTB CONSTRUCTION
Feb 12, 2018Department of Transportation$1,068,368.64IOTB CONSTRUCTION
May 10, 2018Miscellaneous$880,000.00JUDGMENTS AND CLAIMS-NOT REPORTABLE
Oct 10, 2017Miscellaneous$680,110.08JUDGMENTS AND CLAIMS-NOT REPORTABLE
Nov 6, 2017Department of Transportation$673,589.92IOTB CONSTRUCTION
Dec 11, 2017Department of Transportation$667,508.19IOTB CONSTRUCTION
Aug 9, 2017Department of Transportation$636,999.46IOTB CONSTRUCTION
Feb 12, 2018Department of Transportation$621,390.03IOTB CONSTRUCTION
Apr 19, 2018Department of Transportation$593,283.37IOTB CONSTRUCTION
Oct 12, 2017Miscellaneous$476,263.39JUDGMENTS AND CLAIMS-INTEREST
May 14, 2018Department of Transportation$424,504.21IOTB CONSTRUCTION
Jun 5, 2018Department of Transportation$391,652.89IOTB CONSTRUCTION
Jan 16, 2018Department of Transportation$310,660.69IOTB CONSTRUCTION
Oct 3, 2017Department of Transportation$303,763.21IOTB CONSTRUCTION
Mar 7, 2018Department of Transportation$288,560.16IOTB CONSTRUCTION
Dec 11, 2017Department of Transportation$222,502.74IOTB CONSTRUCTION
FY 2017top 20 of 37 payments$34,150,031
DateAgencyAmountCategoryPurchase order
Nov 21, 2016Department of Transportation$5,492,827.70IOTB CONSTRUCTION
Mar 7, 2017Department of Transportation$4,535,267.00IOTB CONSTRUCTION
Jun 19, 2017Department of Transportation$4,180,145.19IOTB CONSTRUCTION
Sep 7, 2016Department of Transportation$3,274,271.92IOTB CONSTRUCTION
Mar 7, 2017Department of Transportation$1,983,262.17IOTB CONSTRUCTION
Feb 8, 2017Department of Transportation$1,501,212.34IOTB CONSTRUCTION
Dec 5, 2016Department of Transportation$1,381,755.23IOTB CONSTRUCTION
May 15, 2017Department of Transportation$1,284,971.39IOTB CONSTRUCTION
Apr 19, 2017Department of Transportation$1,250,220.41IOTB CONSTRUCTION
Mar 27, 2017Department of Transportation$1,066,522.52IOTB CONSTRUCTION
Aug 9, 2016Department of Transportation$1,046,587.66IOTB CONSTRUCTION
Nov 21, 2016Department of Transportation$1,003,182.96IOTB CONSTRUCTION
Jun 19, 2017Department of Transportation$783,777.23IOTB CONSTRUCTION
Oct 11, 2016Department of Transportation$766,880.11IOTB CONSTRUCTION
Sep 7, 2016Department of Transportation$603,284.61IOTB CONSTRUCTION
Jul 25, 2016Department of Transportation$463,154.30IOTB CONSTRUCTION
Nov 21, 2016Department of Transportation$370,023.96IOTB CONSTRUCTION
Mar 7, 2017Department of Transportation$346,222.48IOTB CONSTRUCTION
Feb 8, 2017Department of Transportation$281,477.31IOTB CONSTRUCTION
Jun 19, 2017Department of Transportation$261,259.08IOTB CONSTRUCTION
FY 2016top 20 of 44 payments$17,953,563
DateAgencyAmountCategoryPurchase order
Feb 25, 2016Department of Transportation$2,637,227.86IOTB CONSTRUCTION
Jul 28, 2015Department of Transportation$2,421,156.32IOTB CONSTRUCTION
Mar 22, 2016Department of Transportation$1,128,454.56IOTB CONSTRUCTION
May 24, 2016Department of Transportation$1,123,749.43IOTB CONSTRUCTION
Apr 20, 2016Department of Transportation$1,118,593.86IOTB CONSTRUCTION
Apr 20, 2016Department of Transportation$983,707.50IOTB CONSTRUCTION
Dec 28, 2015Department of Transportation$831,806.19IOTB CONSTRUCTION
Jun 29, 2016Department of Transportation$828,086.43IOTB CONSTRUCTION
Oct 29, 2015Department of Transportation$812,835.41IOTB CONSTRUCTION
Sep 3, 2015Department of Transportation$799,154.91IOTB CONSTRUCTION
Nov 20, 2015Department of Transportation$570,802.76IOTB CONSTRUCTION
Sep 28, 2015Department of Transportation$514,143.17IOTB CONSTRUCTION
Jul 28, 2015Department of Transportation$453,966.51IOTB CONSTRUCTION
Feb 25, 2016Department of Transportation$411,805.03IOTB CONSTRUCTION
Jul 29, 2015Department of Transportation$366,163.92IOTB CONSTRUCTION
Apr 20, 2016Department of Transportation$279,512.18IOTB CONSTRUCTION
Feb 25, 2016Department of Transportation$247,501.93IOTB CONSTRUCTION
Mar 22, 2016Department of Transportation$203,925.21IOTB CONSTRUCTION
May 24, 2016Department of Transportation$201,874.34IOTB CONSTRUCTION
May 24, 2016Department of Transportation$199,920.00IOTB CONSTRUCTION
FY 2015top 20 of 25 payments$11,857,414
DateAgencyAmountCategoryPurchase order
Dec 3, 2014Department of Transportation$4,146,485.91IOTB CONSTRUCTION
Apr 15, 2015Department of Transportation$1,257,043.97IOTB CONSTRUCTION
Jul 29, 2014Department of Environmental Protection$1,225,067.57CONTRACTUAL SERVICES GENERAL
May 18, 2015Department of Transportation$913,753.46IOTB CONSTRUCTION
Dec 3, 2014Department of Transportation$821,666.84IOTB CONSTRUCTION
Jan 22, 2015Department of Transportation$742,274.42IOTB CONSTRUCTION
Oct 30, 2014Department of Transportation$512,127.41IOTB CONSTRUCTION
Jun 12, 2015Department of Transportation$394,236.43IOTB CONSTRUCTION
Sep 2, 2014Department of Transportation$258,539.83IOTB CONSTRUCTION
Apr 24, 2015Department of Environmental Protection$249,000.00CONTRACTUAL SERVICES GENERAL
Apr 15, 2015Department of Transportation$235,680.44IOTB CONSTRUCTION
Dec 3, 2014Department of Transportation$214,954.63IOTB CONSTRUCTION
May 18, 2015Department of Transportation$171,328.77IOTB CONSTRUCTION
Jan 22, 2015Department of Transportation$139,172.63IOTB CONSTRUCTION
Oct 30, 2014Department of Transportation$96,023.89IOTB CONSTRUCTION
Apr 15, 2015Department of Transportation$78,580.55IOTB CONSTRUCTION
Jun 12, 2015Department of Transportation$73,900.21IOTB CONSTRUCTION
Jul 29, 2014Department of Environmental Protection$73,463.19CONTRACTUAL SERVICES GENERAL
May 18, 2015Department of Transportation$57,109.59IOTB CONSTRUCTION
Sep 2, 2014Department of Transportation$48,476.22IOTB CONSTRUCTION
FY 2014top 20 of 22 payments$27,730,567
DateAgencyAmountCategoryPurchase order
Jul 24, 2013Department of Environmental Protection$5,800,664.78CONTRACTUAL SERVICES GENERAL
Dec 4, 2013Department of Environmental Protection$3,500,000.00CONTRACTUAL SERVICES GENERAL
Sep 24, 2013Department of Environmental Protection$3,323,811.51CONTRACTUAL SERVICES GENERAL
Feb 26, 2014Department of Transportation$3,145,788.80IOTB CONSTRUCTION
Jul 9, 2013Department of Environmental Protection$3,037,884.68CONTRACTUAL SERVICES GENERAL
Nov 4, 2013Department of Environmental Protection$3,000,000.00CONTRACTUAL SERVICES GENERAL
Jul 24, 2013Department of Environmental Protection$1,264,020.00CONTRACTUAL SERVICES GENERAL
Apr 25, 2014Department of Environmental Protection$1,163,245.00CONTRACTUAL SERVICES GENERAL
Apr 7, 2014Department of Environmental Protection$1,126,815.52CONTRACTUAL SERVICES GENERAL
Jun 25, 2014Department of Transportation$970,311.81IOTB CONSTRUCTION
Feb 26, 2014Department of Transportation$589,835.40IOTB CONSTRUCTION
Feb 26, 2014Department of Transportation$196,611.80IOTB CONSTRUCTION
Jun 25, 2014Department of Transportation$181,933.46IOTB CONSTRUCTION
Jun 16, 2014Department of Transportation$145,032.80IOTB CONSTRUCTION
Jul 9, 2013Department of Environmental Protection$100,000.00CONTRACTUAL SERVICES GENERAL
Jun 25, 2014Department of Transportation$60,644.49IOTB CONSTRUCTION
May 19, 2014Department of Transportation$60,567.20IOTB CONSTRUCTION
Jun 16, 2014Department of Transportation$27,193.65IOTB CONSTRUCTION
May 13, 2014Department of Environmental Protection$12,000.00CONTRACTUAL SERVICES GENERAL
Jun 16, 2014Department of Transportation$9,064.55IOTB CONSTRUCTION
FY 2013top 5 of 5 payments$87,598,095
DateAgencyAmountCategoryPurchase order
Mar 28, 2013Department of Environmental Protection$37,343,476.66CONTRACTUAL SERVICES GENERAL
Feb 21, 2013Department of Environmental Protection$18,539,525.15CONTRACTUAL SERVICES GENERAL
Mar 22, 2013Department of Environmental Protection$14,016,998.19CONTRACTUAL SERVICES GENERAL
Jun 4, 2013Department of Environmental Protection$13,042,015.82CONTRACTUAL SERVICES GENERAL
Jun 5, 2013Department of Environmental Protection$4,656,079.50CONTRACTUAL SERVICES GENERAL

Recent payments

DateAgencyAmountCategoryMethod
Jun 30, 2025Department of Correction$69,331.31DESIGN-BUILD: BUILDINGSCapital Contracts
Jun 30, 2025Department of Correction$34,426,818.87POLLUTION REMEDIATION OBLIGATIONS DESIGN-BUILD: BUILDINGSCapital Contracts
Jun 24, 2025Department of Transportation$14,991.97IOTB CONSTRUCTIONCapital Contracts
Jun 24, 2025Department of Transportation$32,347.19IOTB CONSTRUCTIONCapital Contracts
Jun 24, 2025Department of Transportation$92,070.38IOTB CONSTRUCTIONCapital Contracts
Jun 24, 2025Department of Transportation$3,143.50IOTB CONSTRUCTIONCapital Contracts
Jun 24, 2025Department of Transportation$16,765.35IOTB CONSTRUCTIONCapital Contracts
Jun 24, 2025Department of Transportation$2,021.70IOTB CONSTRUCTIONCapital Contracts
Jun 24, 2025Department of Transportation$6,065.10IOTB CONSTRUCTIONCapital Contracts
Jun 24, 2025Department of Transportation$23,017.59IOTB CONSTRUCTIONCapital Contracts
Jun 24, 2025Department of Transportation$1,047.84IOTB CONSTRUCTIONCapital Contracts
Jun 24, 2025Department of Transportation$59,967.89IOTB CONSTRUCTIONCapital Contracts
Jun 17, 2025Department of Transportation$197,721.30IOTB CONSTRUCTIONCapital Contracts
Jun 17, 2025Department of Transportation$1,054,513.61IOTB CONSTRUCTIONCapital Contracts
Jun 17, 2025Department of Transportation$65,907.10IOTB CONSTRUCTIONCapital Contracts
Jun 16, 2025Department of Correction$124,646.58DESIGN-BUILD: BUILDINGSCapital Contracts
Jun 16, 2025Department of Correction$25,000.00DESIGN-BUILD: BUILDINGSCapital Contracts
Jun 16, 2025Department of Correction$372,708.96DESIGN-BUILD: BUILDINGSCapital Contracts
Jun 16, 2025Department of Correction$484,064.19DESIGN-BUILD: BUILDINGSCapital Contracts
Jun 16, 2025Department of Correction$1,090,397.42DESIGN-BUILD: BUILDINGSCapital Contracts
Jun 16, 2025Department of Correction$12,500.00DESIGN-BUILD: BUILDINGSCapital Contracts
Jun 16, 2025Department of Correction$377,246.51DESIGN-BUILD: BUILDINGSCapital Contracts
Jun 16, 2025Department of Correction$907,959.04DESIGN-BUILD: BUILDINGSCapital Contracts
Jun 16, 2025Department of Correction$1,411,611.40DESIGN-BUILD: BUILDINGSCapital Contracts
Jun 16, 2025Department of Correction$230,535.75DESIGN-BUILD: BUILDINGSCapital Contracts

Other vendors serving Department of Correction

VerifiedData refreshed Sep 7, 2026 from Checkbook NYC (checkbooknyc.com): 38,060,921 payments on record, Dec 22, 2009 to Jun 30, 2025. How we verify this data